Monday, March 30, 2015

Sanitary Sewer Service Replacement Continues

Work Completed Last Week:
  • Began replacement of sanitary sewer services along Sandy Lane
Work Anticipated Next Week:
·         Continue replacement of sanitary sewer service lines. Contractor will continue to work east along Sandy Lane towards Debra Lane. 

The new sanitary sewer service will be replaced from the sanitary mainline sewer to a point between the existing curb & gutter and the existing sidewalk, depending on existing landscape in the area.

Saturday, March 21, 2015

Underground Utility Work to Begin Next Week

Work Completed Last Week:
  • Grinding of existing asphalt pavement
  • Project layout
  • Saw-cutting of existing pavement
  • Mobilization of equipment and materials
  • Televising of existing sewers
Work Anticipated Next Week:
·         Begin installing sanitary sewer services at all residents. Contractor will begin at the intersection of Sandy Lane and Mary Kay Lane working north and east towards Debra lane.

 The new sanitary sewer service will be installed from the sanitary mainline sewer to a point between the existing curb & gutter and the existing sidewalk, depending on existing landscape in the area.

Monday, March 16, 2015

Preparation Work to Begin this Week

Work Completed Last Week:
  • Resident Preconstruction Meeting -  A copy of the presentation can be emailed to you.  Send requests to Robert Steele at rsteele@glenview.il.us
Work Anticipated Next Week
  • Project layout
  • Saw-cutting of existing pavement
  • Mobilization of equipment and materials
  • Televising of existing sewers
The contractor is anticipated to begin installation of the underground utility work the week of March 23rd.  The contractor will begin with the replacement of sanitary sewer services at each residence.

Tuesday, March 10, 2015

Resident Preconstruction Meeting Scheduled for March 11th

A resident preconstruction meeting is scheduled for Wednesday, March 11th at 6:30 PM. The meeting will be held at the Community Room at the Police Department, 2500 East Lake Avenue.

DiMeo Brothers, prime contractor for the project, will begin mobilizing, saw-cutting, pre-construction televising, and other preparatory work on Monday, March 16th

Excavation work is expected to start on Monday, March 23rd.