Friday, July 10, 2015

Sod Restoration Scheduled Week of July 13th

As you can tell by the reduced activity on-site, the major construction items are now completed. Last week the contractor performed some miscellaneous landscape grading, site clean-up, and various testing and inspections.

Sod restoration is currently anticipated to begin on late this week or early this week of July 13th.

Once all the work is completed, a final walk-through of the project will be completed to determine any items that need repair or additional work to be completed. Once all work is completed, inspections performed, and tests passed; the final lift of asphalt pavement will be installed. We are currently anticipating the final lift of asphalt pavement will be installed by July 24th.