Monday, July 20, 2015

Sod Restoration Completed

This past week, the landscape contractor completed final grading and installation of topsoil. The contractor also completed the sod restoration along the project site. The contractor will continue to water the newly installed sod until it takes root and a healthy stand of grass is established.

This week, we anticipate work in preparation for the final layer of asphalt pavement to be completed. Work will include cleaning the roadway, milling joints, and pavement milling along Mary Kay Lane.

The final lift of asphalt pavement is currently scheduled for the first part of the week of July 27th

Thanks again for all your patience during the construction.