Friday, July 3, 2015

Asphalt Pavement Installed

Work Completed Last Week:
DiMeo Brothers and Peter Baker & Sons Asphalt (Roadway Reconstruction)
·         Graded aggregate base under the roadway
·         Paved first 2 layers of asphalt pavement.
·         Landscape grading
·         Topsoil installation.  

Nicor Gas (Gas Main and Service Replacement)
·         Completed gas main and services replacements.
·         If you have any additional concerns with your gas service, please contact Nicor Gas.

Work Anticipated This Week:
·         Landscape grading
·         Installation of topsoil
·         Installation of sod.

Thank you to all the residents that were without access to their driveways for approximately 1.5 weeks. Your patience and understanding was greatly appreciated. Now that the concrete work and first 2 layers of asphalt pavement are completed, we do not anticipate any further driveway restrictions.

Currently, the contractor is working on the landscape restoration along the entire project site. Once this work is completed, the contractor will begin performing the final inspections and testing prior to finalizing the project. Once all testing and inspections are completed and approved, the final lift of asphalt pavement will be installed. We currently do not have a schedule for this work, but we will provide you an update as the timing is finalized.

Have a safe and happy July 4th Holiday.