Friday, June 12, 2015

Roadway Reconstruction On-Going. Concrete Curb & Gutter Next Week.

Work Completed Last Week:
·         Removal of existing concrete cub & gutter, sidewalks, and driveways
·         Installed temporary access ramps at driveways
·         Roadway excavation
·         Installation of aggregate base course
·         Nicor Gas continued with main line and service replacements 

Work Anticipated This Week:
DiMeo Brothers (Roadway Reconstruction)
·         Roadway excavation
·         Installation of aggregate base course
·         Grading in preparation for concrete curb & gutter.
·         Preparation work prior to concrete curb & gutter
·         Pouring of concrete curb & gutter.
 
Nicor Gas (Gas Main and Service Replacement)
·         Continuation of main line and service replacements.

The roadway excavation portion of the project is currently under way. During this phase, getting around the neighborhood will be difficult due to the number of trucks required and construction operations on-going. During the concrete curb & gutter, driveway, and sidewalk installations, access to driveways will be restricted to allow for the concrete to be poured, allow sufficient curing time, and asphalt pavement to be installed. We anticipate residents will be out of their driveways for approximately 2 weeks once the concrete work begins to having the roadway paved with access restored. Exact timing is yet to be determined, but will likely begin the middle of next week. Residents will be notified of exact timing and parking instructions.

The contractor is also anticipated to work on Saturday, June 13th starting at 8:00 AM

Thank you again for all your patience and understanding during construction.