Work Completed Last Week:
DiMeo Brothers (Roadway Reconstruction)
·         Roadway excavation
·         Installation of aggregate base course
·         Grading in preparation for concrete curb & gutter. 

Nicor Gas (Gas Main and Service Replacement)
·         Continuation of main line and service replacements.

Work Anticipated This Week:
DiMeo Brothers (Roadway Reconstruction)
·         Monday – Install string-line for concrete curb & gutter
·         Tuesday – Grading for concrete curb & gutter
·         Wednesday – Pour concrete curb & gutter
·         Thursday & Friday – Pour concrete curb & gutter, driveways, and sidewalks

Nicor Gas (Gas Main and Service Replacement)
·         Continuation of main line and service replacements.

The rain events throughout the week caused the scheduled concrete work to be pushed back and begin this Monday, June 22nd. Residents within the project site along Debra Lane and Sandy Lane are being asked to please have their vehicles removed from their driveways and garages by Monday, June 22nd by 7:00 AM. We anticipate access will be allowed prior to the July 4th Holiday, once the concrete work is completed and given time to cure as well as having the first 2 layers of asphalt pavement installed.

The Village understands the significant inconvenience that is caused to residents while they are not allowed to access their driveways and garages. The Village is committed to ensuring that access is restored as quickly as possible, but please understand all work is weather dependent. Should additional delays be encountered, residents will be notified with an updated schedule.

Thank you again for all your patience and understanding during the upcoming concrete construction.