Work Completed Last Week:
DiMeo Brothers and TK Concrete (Roadway Reconstruction)
·         Poured concrete curb & gutter
·         Poured concrete driveways and sidewalks

Nicor Gas (Gas Main and Service Replacement)
·         Installed new services to individual homes and made connections to existing meters.
·         If your service was replaced and you need additional work performed, please contact Nicor at the number indicated on the Blue Cards that were left on your door.  

Work Anticipated This Week:
DiMeo Brothers and Peter Baker & Sons Asphalt (Roadway Reconstruction)
·         Monday & Tuesday – Grade aggregate base under the roadway
·         Monday & Tuesday – Rough grading of landscape behind curb & gutter
·         Wednesday & Thursday – Asphalt paving of first two layers.

Nicor Gas (Gas Main and Service Replacement)
·         Complete gas service replacements
·         Disconnect old gas main.

Thank you to all the residents who are without access to their driveways. Your patience and understanding is greatly appreciated. If work is performed as scheduled with no delays in the weather or unforeseen circumstances, the first two layers of asphalt pavement are scheduled to be paved next Wednesday and Thursday. Once this paving is completed, residents will be allowed back into their driveways. If an unexpected or weather delay occurs, residents will be notified regarding the access to their driveways. Every effort possible will be made to ensure all driveway access is restored prior to the July 4th Holiday.