Underground Utility Construction Completed. Nicor Gas to Begin Gas Main and Service Replacement

Work Completed Last Week:
·         Completed the installation of water services.
·         Made final connections between existing water main and new water main.
·         Abandonments within the existing water main system.
·         General site clean-up.
·         100% of Underground Utility Improvements are completed.

Work Anticipated This Week:
·         General site clean-up
·         Demobilization of equipment.

Now that the underground utility improvements are completed, DiMeo Brothers will be demobilizing from the site to allow for Nicor Gas to install new gas mains and services along Debra Lane and Sandy Lane.

We anticipate Nicor Gas will be on-site starting the week of May 11th. It is anticipated it will take them approximately one and a half months to complete the project.