Work Completed Last Week:
·         Removal and grading of sidewalks not adjacent to driveways
·         Pouring concrete sidewalk not adjacent to driveways
·         Demobilization of equipment
 
Work Anticipated This Week:
·         Nicor to begin gas main and service replacement

We are currently working with Nicor to determine their schedule to begin gas main and service replacement along Debra Lane and Sandy Lane. If it appears this construction will be delayed by an extended period of time, the Village may request the contractor to begin roadway reconstruction prior to the Nicor Gas work beginning. Residents will be notified of the on-going construction operations.