Work Completed Last Week:
  • Grinding of existing asphalt pavement
  • Project layout
  • Saw-cutting of existing pavement
  • Mobilization of equipment and materials
  • Televising of existing sewers
Work Anticipated Next Week:
·         Begin installing sanitary sewer services at all residents. Contractor will begin at the intersection of Sandy Lane and Mary Kay Lane working north and east towards Debra lane.